Transportation Projects

Intersection Improvement Projects

The Town of Zebulon is experiencing rapid growth along several major corridors throughout town. As new neighborhoods are built and new residents move into our community, the increased traffic requires changes to our roadways to ease congestion and enable the safe, smooth movement of traffic. The Town is working with the NC Department of Transportation and various engineers, surveyors, contractors, and other firms to design and construct intersection improvements.

The growth in residential neighborhoods along Pippin Road is increasing the traffic at the intersection of Green Pace Road and North Arendell Avenue. A 2017 study by NCDOT indicated that a signal is warranted based on the traffic volumes and delays observed. In March of 2020, the Town of Zebulon hired an engineering firm to study the movements in the area between Green Pace Road, Riley Hill Road, and Proctor Street and to examine the various options for improving safety and traffic flow. The Town, engineers, and NCDOT ultimately decided to install a traffic light at Green Pace Road and North Arendell Avenue and to add turn lanes on North Arendell Avenue.

In October of 2020, the Town began designing the intersection, obtaining permits, and working with utilities in the area. The estimated construction cost is $1.3 million. Once construction is complete, NCDOT will take over all maintenance and repairs.

Intersecton Plan

 

Project Timeline

PROJECT ACTIVITYSTATUS/ TIMEFRAME
Warrant Analysis (NCDOT)COMPLETE - May 2017
Transportation Impact StudyCOMPLETE - Mar 2020
Planning Discussions with NCDOTCOMPLETE - Aug 2020
Maintenance Agreement executed with NCDOTCOMPLETE - Aug 2020
Hire engineer for design, environmental permitting, surveying, utility coordination, & erosion controlCOMPLETE - Oct 2020
Survey existing conditions and elevationsCOMPLETE - Dec 2020
25% Construction plans completedCOMPLETE - Feb 2021
60% Construction plans completedCOMPLETE - Nov 2021
Obtain environmental permitsCOMPLETE
Coordinate with utilities in project areaCOMPLETE
100% Construction Plans approval by NCDOTCOMPLETE
Complete Bid Documents, Estimates, & SpecsCOMPLETE
Contract for ConstructionCOMPLETE
Contract for Construction Administration/CEI ServicesCOMPLETE
Project ConstructionONGOING
Project CloseoutWinter 2023

One area of rapid growth is near the intersection of Shepard School Road and Old Bunn Road/Proctor Street. A traffic study conducted in January of 2020 indicated that the volume of traffic flowing through the intersection would necessitate a light once the new neighborhoods were fully built. While NCDOT has this project in its long-range plans, the Town of Zebulon is moving forward with funding and constructing the improvements now in recognition of the project's importance to the Zebulon community. Once completed, NCDOT will take over all maintenance and upkeep for the intersection, from the monthly power bills to future infrastructure repairs.

Beginning in November of 2020, the Town is working with consultants, NCDOT, and other state agencies to install turn lanes and traffic signals at this intersection. The final design will improve safety and the flow of traffic. The estimated construction cost is $1.7 million.

While the Town of Zebulon works to implement these improvements, which typically take 3-4 years from design to construction, NCDOT is installing an All Way Stop at this intersection to address safety concerns and traffic back-ups on Old Bunn Road and Proctor Street.

Intersecton Plan

 

Project Timeline

PROJECT ACTIVITYSTATUS/ TIMEFRAME
Warrant AnalysisCOMPLETE - Jan 2020
Planning discussions with NCDOTCOMPLETE - Fall 2020
Maintenance Agreement executed with NCDOTCOMPLETE - Jan 2021
Hire engineer for design, environmental permitting, surveying, utility coordination, & erosion controlCOMPLETE - Nov 2020
Survey existing conditions and elevationsCOMPLETE - Mar 2022
30% Construction plans approval from NCDOTCOMPLETE - April 2021
60% Construction plans approval from NCDOTCOMPLETE - Nov 2021
Obtain environmental permitsCOMPLETE - Jan 2022
Secure buffer mitigation creditsCOMPLETE - Jan 2022
Hire right-of-way (ROW) agentCOMPLETE - Mar 2022
Purchase Easements and ROWONGOING
Design water line relocationsONGOING
100% Construction Plans approval by NCDOT Spring 2023
Complete Bid Documents, Estimates, & Specs Spring 2023
Contract for ConstructionFall 2023
Contract for Construction Administration/CEI ServicesFall 2023
Project ConstructionSpring - Fall 2024
Project CloseoutFall 2024